...
landfill-design-case study

Landfill Extension Case Study

Landfill Extension Contract for a Sanitary Landfill, North Cyprus funded by EuropAid

landfill-design-case study

IPPTS Associates Role: Leachate Expert, Landfill Expert, and Team Leader

Responsible for leachate treatment and landfill extension design for the landfill, which serves the whole of the north of the island of Cyprus.

Work included reporting on green waste composting and construction waste recycling options.

Responsible for specification, bill of quantities, and provision of all contract documents.

Frequently Asked Questions

How long did the landfill extension project take?

The landfill extension project took approximately 3 years to complete.

What were the main environmental concerns addressed during the project?

The main environmental concerns addressed during the project included:

  • leachate accumulation within the landfill
  • lack of leachate treatment and disposal
  • lack of cellular development of the landfill base, resulting in the collection of large quantities of leachate
  • stability of waste slopes and a large bund.

These were mitigated through:

  • design provision for a leachate treatment facility with evaporation in leachate evaporation ponds
  • future planned cellular design to minimize leachate generation
  • structural stability assessment with calculations was completed, resulting in changes to site structures and operational practices.

How did the community react to the extension project?

The community’s reaction to the extension project varied. Initially, there was some opposition and skepticism, but through effective communication and engagement, we were able to address concerns and gain community support.

What were the major technical challenges faced during the project?

The major technical challenges faced during the project included

  • Designing for construction by the local workforce with no previous experience in landfill development.
  • Managing stormwater during construction required innovative engineering solutions and technologies to overcome.

What measures were taken to ensure the project’s compliance with regulations?

To ensure compliance with regulations, we implemented site personnel training, which included guidance on the risk of landfill gas explosions, etc. These measures were regularly monitored and evaluated to ensure adherence to environmental standards.

How was the project funded?

The project was funded through EU funding sources. The funding was secured through partnerships and EU Commission support.

What were the long-term benefits of the landfill extension?

The long-term benefits of the landfill extension include:

  • Long-term capacity to accept waste at the landfill
  • Leachate management and disposal are now provided
  • Increased landfill capacity, extended lifespan,
  • Positive environmental impact, and improved waste management practices.

 


You May Also Like These Topics...
Waste Management DSEAR Risk Assessment case study

DSEAR Risk Assessment for a Waste Treatment Facility Located on a Capped Landfill

DSEAR Risk Assessment Service DSEAR Risk Assessment and Explosion Protection Document provided for a waste processing facility located above a capped, but large and deep heavily gassing landfill in Wales. Features: Site visit with in-depth interview of facility operatives to scope the potential landfill gas health and safety risks Production of risk assessment table with […]

leachate pollution incident environmental emissions compliance advice

Case Study 8: Leachate Pollution Environmental Compliance – Water Chemistry Expert Service

[su_heading size=”18″]IPPTS Associates Role:[/su_heading] Leachate Water Chemistry Expert Client in East Anglia, UK. Reporting, remedial works inspection, and regulatory authority liaison in connection with a problem with environmental emissions compliance including independent advice on water quality sampling data interpretation after a pollution incident in connection with an anaerobic digestion facility (biogas plant). Worked to repair […]

in-vessel composting case study environmental waste processing

Case Study 7: In-Vessel Composting Facility Design

[su_heading size=”18″]IPPTS Associates Role:[/su_heading] General waste management expert, and composting process design Developed the process design and provided engineering advice, to Glonet Consultants, for the feasibility studies for two large In-vessel MSW Composting Facilities planned for two municipalities in India. Estimated at £15 Million to £19 Million construction cost.

Leachate storage tank environmental compliance consultant

Methane Stripping from Landfill Leachate: A Case Study

For this case study on Methane Stripping from Landfill Leachate, IPPTS Associates’ role was to act as the leachate expert for a centralized methane stripping facility to serve 4 landfills in the counties of Yorkshire and Derbyshire. Duties were to design a methane stripping plant (MSP) in outline, write up the technical specs, and procure […]

Tags: , , ,
Previous Post
closed landfill
Case Studies of IPPTS Associates Consultancy Projects

Leachate Management Case Studies at Closed Landfills

0 Shares
Tweet
Pin
Share
Share
Share